Lease Summary for the proposed power plant project
CITY OF JASPER
JASPER CLEAN ENERGY CENTER
July 21, 2011
|
TOPIC |
EXPLANATION |
REFERENCE |
| Landlord: | The City of Jasper |
Preamble |
| Tenant: | Jasper Clean Energy, LLC |
Preamble |
| Premises: | 1163 E. 15th Street, Jasper, Indiana (approximately 6.5 acres) |
Preamble Exhibit 1 |
| Term of Phase I:(Interim Period) | Effective Date to Commencement Date(12 to 18 months) |
Preamble |
| Term of Phase II:(Construction Period) | Commencement Date to Commercial Operation Date(18-24 months) |
Preamble |
| Term of Phase III:(Operational Period) | Commercial Operation Date to End of Lease(20 years + option) |
Preamble |
| Term of Phase IV:(End of Lease) | Decision for Use of Facility
|
Preamble |
| Initial Lease Term: | 20 years from Commercial Operation Date |
p. 2 |
| Construction Term: | 18-24 months |
p. 2 |
| Renewal Options | Two 5-year Renewal Terms |
p. 2 |
| Rent: |
o $425,000 [Paid during Phases II and III] o Inflation increases for Annual Rent (100% of Implicit Price Deflator).
o $1.5 per MWh [Paid during Phase III] o Inflation increases for Royalty (100% of Implicit Price Deflator). o Based on production of electricity by Modified Boiler)
|
p. 4 |
| Blackout Event: |
|
p. 46 |
| Repairs & Maintenance: |
p. 40 |
|
| Utilities: |
Article XXII |
|
| Insurance: |
Article X Exhibit 20 |
|
| Property Taxes: |
Article XXIII |
|
| Improvements: |
Article IX Exh. 5 / Exh. 11 |
|
| Conditions Precedent:(applicable during Phase I) |
o Inability to obtain environmental permits.o Inability to obtain interconnection agreement to Grido Inability to obtain power sales agreement.o Inability to obtain construction funding.o Inability to obtain natural gas pipeline agreement.o Inability to obtain government approvals.o Inability to obtain 69KV service line agreement.o Inability to obtain tax abatement.
o If Conditions Precedent above not met by September 2012 (Commencement Date) o Subject to Lessee’s right to demonstrate substantial effort to comply with and progress towards satisfaction of any of those Conditions Precedent |
p. 15 |
| Fuel Limitations: |
|
Article V p. 45 |
| Commit to Miscanthus: |
|
p. 38 |
| Security / Liquidated Damages: |
$1.5 Million Sinking Fund
|
p. 20-22 p. 48-49 |
| Coordination Committee: |
|
p. 33 |
| Emissions: |
|
Exhibit 14 |
| Right of First Refusal: |
p. 47 |
|
| Site Location: |
Exhibit 1 |
|
| Description of Existing Plant: |
Exhibit 2 |
|
| Description of Remaining Equipment: |
Exhibit 5 |
|
| Offer of Employment to Existing Employees: |
Exhibit 7 |
|
| Qualifications of Facility Manager: |
Exhibit 15 |
|
| Construction Control Qualifications: |
Exhibit 16 |
|
| Sustainability / Fire Protection: |
Exhibit 17 |
|
| Access to and Right of Inspection: |
p. 18 |
|