Jasper paving begins Friday; several streets affected (updated schedule)
Due to a conflict in scheduling with the contractor, JH Rudolph, the paving schedule below has been CHANGED to Monday, October 2,Tuesday, October 3 and Wednesday, October 4 instead of Friday.
The Jasper Street Department and JH Rudolph will be paving those streets which were milled last week beginning Monday. They will begin on Terrace Ave first thing Friday morning. Paving includes Terrace Avenue in its entirety; Worrell Drive in its entirety; 41st Street from Portersville Road to Baden Strasse; 44th Street from Obing Strasse to Baden Strasse; Obing Strasse in its entirety; and the intersection of Baden Strasse and Manneheim Road just west of U.S. 231.